29/6
30
• 03:30 AMNS 1000 TPD - Rotoflow
• 04:00 INOX Air/KESG - Weekly Meeting for ESG Warehouse Design
• 21:30 VPSA- Pioneer meet-
1/7
• 02:30 350 TPD LMEL: Project Meeting with LMEL
• 05:30 Rotoflow Updates for Bokaro & AMNS
• 21:30 Monthly Plant Updates - All SMR plants. (Bhiwadi, Vile Bhaghad, Sriperumbudur)
• 22:30 Weekly Review – Bokaro Insurance Claims
2
• 21:30 Monthly Plant Updates - Dahej ATC & GFL, ATC Vizag, Premier
3
• 02:30 Tata Meramandali Review
• 03:30 Monthly Plant Updates - Bhandara
• 21:30 Monthly Plant Updates - Hospet
• 22:30 FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
• 22:30 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
• 23:30 350 TPD Lloyds_Weekly Review with XLA
4
• 03/07/2025 FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
• 03/07/2025 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
• 01:30 INOX Air/KESG - Weekly Meeting for ESG Warehouse Design
• 21:30 RE: Request for Quotation - 2700 Nm³/Hr Nitrogen Generator (Skid-Based Plant)
• 23:30 DISCUSSION ON MOTORS REPLACEMENT - 1250 TPD
5
• 04/07/2025 DISCUSSION ON MOTORS REPLACEMENT - 1250 TPD
• 02:30 Monthly Plant Updates All Large ASUs & Onsite Gas plants.
6
7
• 02:30 Salem Renewal Offer- meeting with Chairman
• 03:30 L & G Purifier
• 22:30 FW: NML Project Review
• 23:30 INOX AIR PRODUCTS PERSONAL INTERVIEW AT THANE A/2 OFFICE ON 08.07.2025 @ 12 P.M
8
• 02:30 ZOOM Meeting Link - 2000 TPD plant PGTR discussion
• 02:30 350 TPD LMEL: Project Meeting with LMEL
• 04:00 Quarterly EHS Review_INOX Air Products
• 04:00 Quarterly EHS Review_INOX Air Products
9
• 02:30 [External] Bokaro 2000 TPD - PGTR - 2nd Meeting
• 21:30 Monthly Plant Updates - Hazira
• 22:30 Weekly Review – Bokaro Insurance Claims
10
• 01:30 INOX Air/KESG - Weekly Meeting for ESG Warehouse Design
• 02:30 FW: Inox Air Products- Claims Discussion
• 02:30 Tata Meramandali Review
• 21:30 Monthly Plant Updates - N20 plants
• 22:30 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
• 23:00 Unloading of ESG packages from Containers at PG | zoom call 11th July 11:30am to 12:15pm
• 23:30 350 TPD Lloyds_Weekly Review with XLA
11
• 10/07/2025 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
12
13
• 23:30 Demo Session: Webinar on Connecting the Nation with RE through ISTS: How India’s C&I Consumers Can Access Large Scale Green Power
14
• 13/07/2025 Demo Session: Webinar on Connecting the Nation with RE through ISTS: How India’s C&I Consumers Can Access Large Scale Green Power
• 21:30 Monthly Plant Updates - Salem & Tirunelveli ATG
15
• 02:30 FW: Cryostar's confirmation on action-plan with time-line against G231A Cryo pump motor failures-issue in AMNS 1000 TPD Hazira site - V.URGENT & CRITICAL
• 02:30 350 TPD LMEL: Project Meeting with LMEL
• 21:30 Monthly Plant Updates - Jaghadia UPL & Ceat Halol,
16
• 02:30 Webinar: Connecting the Nation with RE through ISTS: How India’s C&I Consumers Can Access Large Scale Green Power
• 02:30 <No Subject>
• 21:30 Personal Interview- Electrical Team- Harshal
17
• 02:30 Tata Meramandali Review
• 22:30 FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
• 22:30 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
• 23:30 350 TPD Lloyds_Weekly Review with XLA
18
• 17/07/2025 FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
• 17/07/2025 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
• 00:00 FW: Bokaro Balance Spares Discussion
• 21:30 Monthly Plant Updates - Bokaro
• 22:30 280 TPD_TSLL Review Meeting
19
• 18/07/2025 280 TPD_TSLL Review Meeting
20
• 22:00 You have [7] undelivered mails
21
• 20/07/2025 You have [7] undelivered mails
• 00:00 james meeting
• 00:00 g
• 01:30 INOX Air/KESG - Weekly Meeting for ESG Warehouse Design
• 22:30 FW: NML Project Review
22
• 02:30 350 TPD LMEL: Project Meeting with LMEL
23
• 22:30 FW: : NML 120 TPD - Commissioning status
• 22:30 INOXAP - Green Hydrogen Certification for Asahi
• 23:00 Discussion on High Approach temp in Coolers
24
• 01:30 INOX Air/KESG - Weekly Meeting for ESG Warehouse Design
• 02:30 Tata Meramandali Review
• 22:30 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
• 23:30 350 TPD Lloyds_Weekly Review with XLA
25
• 24/07/2025 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
• 03:00 Sriperumbudur Hydrogen Plant Safety Audit closing meeting
26
27
28
• 02:00 Rotoflow Updates for Bokaro & AMNS
29
• 00:30 RE: Reminder for submission of delay analysis _Re: TPSL Letter to INOX - Delay in commissioning of N2 Generator Plant Dtd : 07.06.2025
• 01:30 Rotoflow Updates for Bokaro & AMNS
• 03:30 350 TPD LMEL: Project Meeting with LMEL
• 22:30 Weekly Review – Bokaro Insurance Claims
30
31
• 01:30 INOX Air/KESG - Weekly Meeting for ESG Warehouse Design
• 02:30 Tata Meramandali Review
• 21:30 Monthly Plant Updates - Hospet
• 22:30 FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
• 22:30 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
• 22:30 Reminder for submission of delay analysis _Re: TPSL Letter to INOX - Delay in commissioning of N2 Generator Plant Dtd : 07.06.2025
• 23:30 350 TPD Lloyds_Weekly Review with XLA
1/8
• 31/07/2025 FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
• 31/07/2025 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
2
• 02:30 Monthly Plant Updates All Large ASUs & Onsite Gas plants.
3
4
• 21:30 Monthly Plant Updates - Bhandara
• 22:30 FW: NML Project Review
5
• 02:30 350 TPD LMEL: Project Meeting with LMEL
• 05:00 PERIC Electrolysers
• 21:30 Monthly Plant Updates - All SMR plants. (Bhiwadi, Vile Bhaghad, Sriperumbudur)
• 22:30 Weekly Review – Bokaro Insurance Claims
6
• 21:30 Monthly Plant Updates - Dahej ATC & GFL, ATC Vizag, Premier
7
• 02:30 Tata Meramandali Review
• 21:30 Monthly Plant Updates - N20 plants
• 22:30 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
• 23:30 350 TPD Lloyds_Weekly Review with XLA
8
• 07/08/2025 FW: Nitrogen Plants Update (NML/Chennai-PHG/Other)
9
Calendar.ics