Day View Day Work Week View Work Week Week View Week Month View Month
Go to today Today
go to previous page August 2023 go to next page
August 2023
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
30/7
 
 
 
 
31
•  02:30   220KV GIS AT TATA MERAMANDALI - ODHISA-Commercial terms
•  06:00   Meramandali GIS EPC
1/8
•  02:30   INOX discussion
•  03:30   Safety Reboot Work Shop
•  04:00   Oxygen Purifier of Asahi Project
•  23:00   Commercial Terms and Condition-220kv GIS Substation
•  23:30   AMNS 1000 TPD
2
•  01/08/2023   Commercial Terms and Condition-220kv GIS Substation
•  01/08/2023   AMNS 1000 TPD
•  00:00   Animated Safety Induction Video for Inox AP
•  01:00   Meeting for Narmadapuram Plant issue
•  02:00   FW: SAIL BOKARO - Impeller Repair
•  22:30   GIS - TATA
3
•  00:00   INOX-AP: Discussing & freezing of 3D induction movie requirements
•  01:00   220kv GIS s/s- Delivery schedule
•  02:30   FW: TATA 2X1800 TPD Project Review Meeting
•  22:00   FW: Weekly review meeting for 2 X 1800 TPD ASU Project update.
•  22:30   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
4
•  03/08/2023   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
•  01:30   HAZOP_INOXAP SCOPE H2 Electorlyser_AISG PROJECT
•  06:15   GIS 220 KV-Vendor selection
•  21:00   HAZOP_INOXAP SCOPE H2 Electorlyser_AISG PROJECT
•  22:30   Discussion on Solar Module vendor
5
•  04/08/2023   HAZOP_INOXAP SCOPE H2 Electorlyser_AISG PROJECT
•  02:30   AspenTech Solution requirement Discussion
•  03:30   AURIC Benefits status update
6
•  23:50   FW: SAIL Bokaro - HVAC Power Distribution
 
 
 
7
•  06/08/2023   FW: SAIL Bokaro - HVAC Power Distribution
•  02:30   Why - why tree for LOX pump strainer choking issue
•  04:30   HT Power at Barjora
•  22:30   FW: NML Project Review
•  23:35   Internal discussion on impeller repair by M/s STC
8
•  07/08/2023   Internal discussion on impeller repair by M/s STC
•  00:30   CONSTRUCTION CLEARANCE-CT Change by INOX AIR: Requirement of BG details
•  22:30   FW: Clarifications on MAC & BAC motor comments - INOX TSL, Meramandali project
•  23:30   Barjora Power for new L-200
9
•  01:30   Sitting Arrangement_3rd Floor_ A2 Office
•  02:00   FW: Follow up meeting - Narmadapuram Incentive
•  04:00   AMNS 1000 TPD
•  22:30   AMNS&TSL- ABB GTC Discussion
•  23:30   FW: Discussion on Motor comments - INOX A/c TATA Meramandali
10
•  09/08/2023   FW: Discussion on Motor comments - INOX A/c TATA Meramandali
•  01:30   Discussion on STC & GTC -220KV GIS
•  02:30   FW: TATA 2X1800 TPD Project Review Meeting
•  22:00   FW: Weekly review meeting for 2 X 1800 TPD ASU Project update.
•  23:30   Tamil Nadu Captive Wind & Solar Power Purchase
11
•  10/08/2023   Tamil Nadu Captive Wind & Solar Power Purchase
•  01:30   FW: Aspen Tech Product demo
•  01:30   Discussion on GTC & STC_INOX
•  06:00   Tamil Nadu Captive Wind & Solar Power Purchase
12
13
 
 
 
 
14
15
16
17
•  02:30   FW: TATA 2X1800 TPD Project Review Meeting
•  22:00   FW: Weekly review meeting for 2 X 1800 TPD ASU Project update.
•  22:30   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
18
•  17/08/2023   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
•  03:30   AMNS 1000 TPD
•  04:00   INOXAP- ABB Discussion on GTC
•  04:30   XLA Proposal refresh
•  23:30   Asahi Glass Project Plant Layout Review
19
•  18/08/2023   Asahi Glass Project Plant Layout Review
•  03:15   Discussion on GTC_220KV GIS_Meramandali_Inox
20
 
 
 
 
21
•  02:00   AspenTech session on IP 21, visualisations platform Data works
•  04:30   Proposed Safety Re-Boot Awareness Workshop
•  22:30   EHV Review Meeting
•  22:30   FW: NML Project Review
•  23:30   INOX-AP: Discussing on the concerns w.r.t to execution of 3D induction movie requirements
22
•  21/08/2023   INOX-AP: Discussing on the concerns w.r.t to execution of 3D induction movie requirements
•  02:00   FW: N2O plant - MOM Update/Review
•  03:30   [External] RE: L200: Lesson learnt sharing with INOXAP for new L200 Plants(Vizag,Barotiwala and Blr)
•  05:00   Renewable Power updates
23
•  03:30   AMNS 1000 TPD
•  04:30   Seminar preparations review
24
•  02:30   FW: TATA 2X1800 TPD Project Review Meeting
•  03:30   PPA and SHA discussion
•  04:00   FW: Tata Steel Ludhiana 180tpd ASU
•  22:00   FW: Weekly review meeting for 2 X 1800 TPD ASU Project update.
•  23:30   Kick Off Meeting For 220 KV GIS Project along with 3 x 65 MVA Transformers at Meramandali, TATA Steel Site under M/s INOX Air Products Pvt. Ltd.
•  23:30   FW: AURIC Power and Incentive status update
25
•  24/08/2023   Kick Off Meeting For 220 KV GIS Project along with 3 x 65 MVA Transformers at Meramandali, TATA Steel Site under M/s INOX Air Products Pvt. Ltd.
•  24/08/2023   FW: AURIC Power and Incentive status update
•  02:00   Foxconn Bangalore site co ordinates
•  04:00   DG Sets
26
27
•  23:30   Specialty Gases Provisions
 
 
 
28
•  27/08/2023   Specialty Gases Provisions
29
30
31
•  02:30   FW: TATA 2X1800 TPD Project Review Meeting
•  21:30   Monthly Plant Updates - Hospet
•  22:30   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
1/9
•  31/08/2023   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
•  02:15   Cooling Water System & Coolers in our ASU
•  03:00   General meeting on Renewable Energy & OA trends
•  23:00   HAZOP_INOXAP SCOPE H2 Electorlyser_AISG PROJECT
2
•  01/09/2023   HAZOP_INOXAP SCOPE H2 Electorlyser_AISG PROJECT
•  04:30   KPI based Appraisal system
3
•  21:30   Inox Air - Cleantech
 
 
 
4
[External] FW: 2000TPD Oxygen Plant, FAT Motors and MCPs
•  00:00   TSL- Ludhiana- 280TPD
•  02:00   Mini & Major Micron - Equipment dash board & Project broad presentation
•  02:00   Neometaliks_Jyotech - GOX compressor - Progress report for August 2023
•  03:30   JK Tyre Chennai GAN Compressor
•  04:00   INOXAP-ATLAS COPCO- NML 120 TPD ASU- MAC- Monthly Review Meeting- for August 2023.
•  21:30   Monthly Plant Updates - Bhandara
•  22:30   FW: NML Project Review
5
[External] FW: 2000TPD Oxygen Plant, FAT Motors and MCPs
•  02:00   NML _ GAN compressor - PO 4500267250- Regarding Monthly progress report August 2023.
•  21:30   Monthly Plant Updates - All SMR plants. (Bhiwadi, Vile Bhaghad, Sriperumbudur)
6
[External] FW: 2000TPD Oxygen Plant, FAT Motors and MCPs
•  03:30   AMNS 1000 TPD
•  21:30   Monthly Plant Updates - Dahej ATC & GFL, ATC Vizag, Premier
•  22:00   FW: Meeting - XLA x INOXAP
7
[External] FW: 2000TPD Oxygen Plant, FAT Motors and MCPs
•  02:00   NML 120 TPD- MAC Suction filter- M/s Spectrum- Monthly progress report August 2023
•  02:30   FW: TATA 2X1800 TPD Project Review Meeting
•  03:30   Showbizz MIS & Dashboard @ INOXAP
•  04:00   PGP Glass Discussions
•  21:30   Monthly Plant Updates - N20 plants
8
[External] FW: 2000TPD Oxygen Plant, FAT Motors and MCPs
•  01:30   Waaree Energies_Gases Requirement(Chikhali & Odisha)
9
[External] FW: 2000TPD Oxygen Plant, FAT Motors and MCPs
ics Calendar.ics GMT -08:00 US/Canada Pacific