25/6
•  23:30   FBT Design of 6200cu.mt
•  23:30   OAL200_Oil flow meter for DE & NDE end
 
 
26
•  25/06/2023   FBT Design of 6200cu.mt
•  25/06/2023   OAL200_Oil flow meter for DE & NDE end
•  02:00   FW: RE: FINAL ENQUIRY DOCUMENTS FOR 220KV GIS AT TATA MERAMANDALI - ODHISA
•  22:30   FW: NML Project Review
27
•  22:00   ZOOM INTERVIEW FOR SUITABLE POSITION IN SITE CONSTRUCTION ON 27-JUN-2023 AT 10:30 AM
28
•  03:30   AMNS 1000 TPD
29
•  22:00   FW: Weekly review meeting for 2 X 1800 TPD ASU Project update.
30
•  02:00   ONLINE HEARING ON APR PETITION OF DVC FOR THE YEARS 2017-18,2018-19 AND 2019-20
1/7
•  02:00   ZOOM INTERVIEW FOR SUITABLE POSITION IN SITE CONSTRUCTION ON 01-JUL-2023 AT 02:30 PM
2
•  23:30   SAP PM Module Training-BAROTIWALA UNIT
 
 
 
3
•  02/07/2023   SAP PM Module Training-BAROTIWALA UNIT
4
•  23:00   Kick off meeting_TATA Meramandali
5
6
•  02:30   FW: TATA 2X1800 TPD Project Review Meeting
•  03:30   TATA Solar Nitrogen Generator
•  22:00   FW: Weekly review meeting for 2 X 1800 TPD ASU Project update.
•  22:30   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
7
•  06/07/2023   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
8
9
•  23:30   SAP PM Implementation - Priority 5 (Surajpur/Pondy) and Priority 6 (Butibori/Hyderabad)
 
 
 
10
•  09/07/2023   SAP PM Implementation - Priority 5 (Surajpur/Pondy) and Priority 6 (Butibori/Hyderabad)
•  22:30   FW: NML Project Review
11
12
•  03:30   AMNS 1000 TPD
13
•  02:30   FW: TATA 2X1800 TPD Project Review Meeting
•  22:00   FW: Weekly review meeting for 2 X 1800 TPD ASU Project update.
14
15
16
 
 
 
 
17
18
•  02:00   FW: BOKARA Project review
•  03:30   FW: AMNS 1000 TPD Project review
•  06:00   FW: TATA Nitrogen Generator - New Technology
19
•  02:00   FW: INOX BOO offer Technical closure
•  03:30   Discussion on proposed EHS Reboot Workshop
•  03:30   AMNS 1000 TPD
•  03:30   Discussion on proposed EHS Reboot Workshop
•  23:30   Update meeting related to safety
20
•  19/07/2023   Update meeting related to safety
•  02:30   FW: TATA 2X1800 TPD Project Review Meeting
•  04:45   Discussion - 220KV GIS AT TATA MERAMANDALI - ODHISA
•  22:00   FW: Weekly review meeting for 2 X 1800 TPD ASU Project update.
•  22:30   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
•  22:30   Meeting with Inox Team - Tomorrow at 11am
•  23:30   Discussion on VITT Camera
•  23:30   Introduction meeting:: Adani & Inox
21
•  20/07/2023   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
•  20/07/2023   Discussion on VITT Camera
•  02:30   Reschedule Meeting on Discussion on proposed EHS Reboot Workshop-
22
23
•  22:30   Double Column High Purity N2 Plant Discussion
 
 
 
24
•  02:30   FW: Meeting request - INOXAP
•  03:30   FW: OA30 1000 TPD AMNS: Executive Review Meeting
•  05:00   Discussions on module requirements
•  22:30   FW: NML Project Review
•  22:30   MAC 3rd stage impeller repair.
25
•  02:00   Power Updates
•  02:30   Meeting - Fourth Partner Energy x INOXAP
26
•  05:00   INOX - Agreement Discussion
27
•  02:30   Topic: Chemical Safety
•  02:30   FW: TATA 2X1800 TPD Project Review Meeting
•  05:00   AAA010998 - WRFQHT753_RFQ of CW and SSF Pumps_INOX/AMNS, 1000 TPD, HAZIRA
•  22:00   FW: Weekly review meeting for 2 X 1800 TPD ASU Project update.
•  22:30   Planning Pavan Sir's Felicitation
28
•  03:30   AMNS 1000 TPD
•  05:00   Inox Air Products - Cleantech
•  21:30   INOX Commercial discussion
•  22:30   Zoom meeting invitation - AMKR Argon Box discussion
29
30
 
 
 
 
31
•  02:30   220KV GIS AT TATA MERAMANDALI - ODHISA-Commercial terms
•  06:00   Meramandali GIS EPC
1/8
•  02:30   INOX discussion
•  03:30   Safety Reboot Work Shop
•  04:00   Oxygen Purifier of Asahi Project
•  23:00   Commercial Terms and Condition-220kv GIS Substation
•  23:30   AMNS 1000 TPD
2
•  01/08/2023   Commercial Terms and Condition-220kv GIS Substation
•  01/08/2023   AMNS 1000 TPD
•  00:00   Animated Safety Induction Video for Inox AP
•  01:00   Meeting for Narmadapuram Plant issue
•  02:00   FW: SAIL BOKARO - Impeller Repair
•  22:30   GIS - TATA
3
•  00:00   INOX-AP: Discussing & freezing of 3D induction movie requirements
•  01:00   220kv GIS s/s- Delivery schedule
•  02:30   FW: TATA 2X1800 TPD Project Review Meeting
•  22:00   FW: Weekly review meeting for 2 X 1800 TPD ASU Project update.
•  22:30   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
4
•  03/08/2023   FW: Nitrogen Plants Update (ATC/JKTI/Bhiwad)
•  01:30   HAZOP_INOXAP SCOPE H2 Electorlyser_AISG PROJECT
•  06:15   GIS 220 KV-Vendor selection
•  21:00   HAZOP_INOXAP SCOPE H2 Electorlyser_AISG PROJECT
•  22:30   Discussion on Solar Module vendor
5
•  04/08/2023   HAZOP_INOXAP SCOPE H2 Electorlyser_AISG PROJECT
•  02:30   AspenTech Solution requirement Discussion
•  03:30   AURIC Benefits status update